15/07/2015
Over the summer months, a number of our overseas suppliers cease manufacturing for a specific length of time. This practice is commonplace in Europe and all staff members take their annual leave during this period. As a result, the companies’ lead times will be longer than usual, and we ask that you read the following schedule to see how the Summer Hiatus affects you and the product(s) you wish to purchase.Please note that the list below, although extensive, only shows the companies that manufacture items for sale on our website. If you have an existing order, or are looking to place one over the coming months, please ask your sales consultant or visit one of our showrooms for further details on other specialist products.
Supplier | Last Order Fulfilment Date | Length of Hiatus | Extra Notes |
Adamsez | 26/06/2015 | 10 weeks | Applies to Hoxton bath surround |
Adatto Casa | Lacquered finishes 28/06/15 Wooden finishes 17/07/15 |
8 weeks | |
Bette | 20/06/2015 | 10 weeks | All Bette products unless held in C.P. Hart stock including Jazz 4, Jazz Solo, basic and trays if not in stock |
Bisazza | 19/06/2015 | 11 weeks | |
Catalano | 17/07/2015 | 10 weeks | Affects our own Zone and Giro as well as specials |
Columbo | 17/07/2015 | 10 weeks | |
Consulto | 26/06/2015 | 10 weeks | |
Cosmic | 6 weeks | ||
Décor Walther | 19/06/2015 | 11 weeks | |
Gessi | 17/07/2015 | 10 weeks | |
Glass Design | 10/07/2015 | 8 weeks | |
Grange | 19/06/2015 | 10 weeks | All MGS, Original, Arc, Waterloo, Ocean |
Imperial | 17/07/2015 | 6 weeks | Affects all London products |
Jorger | 26/06/2015 | 10 weeks | Affects Charleston Arc and Charleston Square |
Keuco | 26/06/2015 | ||
La Torre | 24/07/2015 | ||
Mastella | 26/06/15 for LUX 10/07/15 for Matt/Pearl 17/07/15 for Wood |
||
Nickles | 26/06/2015 | Manufacturers of Moto and other items from Crosswater | |
Recor | 03/07/2015 | Freestanding baths including our own if not in stock | |
Schneider | Add 2-3 weeks onto lead time |